Site 00011572 - Tom creek at Km 34.9 Robert Campbell Highway
-
Status
Confirmatory sampling completed. No further action required. -
Site Status
Closed -
Classification
Medium Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
Federal activities -
Property Type
Non-Federal (Provincial Government)
Site Location
-
Latitude, Longitude
60.290555, -129.02055 -
Municipality
Yukon, Unorganized, YT -
Federal Electoral District
Yukon
Site Management Strategy
- Other
Contaminant Details
Contamination Estimate
-
Cubic Meters
15 -
Hectares
1 -
Tons
30
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
PAHs (polycyclic aromatic hydrocarbon) | Soil |
Action Plan
The hydrometric network uses different methods to measure water levels. One method involves the use of wells constructed with creosote treated wood. As scientific understanding of creosote evolved it was discovered that sources treated with these chemicals may adversely affect the environment. In order to correctly assess its liability at each site, WSC plans to begin investigating hydrometric stations that used wood treated with these chemicals in fiscal year 08-09.
Additional Information
During the fiscal year 08-09, Water Survey Canada will be performing assessments only in order to identify the stations with contamination.
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 0 |
5 km | 0 |
10 km | 0 |
25 km | 0 |
50 km | 1,196 |
Summary of Annually Reported Data
Total Expenditures
-
Assessment
$142,288.25 -
Remediation
$169,820.00
FCSAP Expenditures
-
Assessment
$102,016.87 -
Remediation
$144,347.00
Financial/Annual Information
2022-2023click to collapse contents
2022-2023
Reporting Organization
Environment and Climate Change CanadaInternal Identifier
00011572Highest Step Completed
09 Confirmatory Sampling and Final ReportingTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$37,940.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$32,249.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
11 tClosed
Yes
- Version:
- 42