Site 00025781 - Wasagaming Drive Commercial Property
-
Status
Confirmatory sampling completed. Long term monitoring underway. -
Site Status
Active -
Classification
Medium Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
National Park of Canada -
Property Type
Canada Lands
Site Location
-
Latitude, Longitude
50.656214, -99.971777 -
Municipality
Division No. 17, Unorganized, MB -
Federal Electoral District
Dauphin--Swan River--Neepawa
Site Management Strategy
- Remediation
- Additional assessment
- Risk Management
Contaminant Details
Contamination Estimate
-
Cubic Meters
3,000
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
PHCs (petroleum hydrocarbons) | Groundwater |
PHCs (petroleum hydrocarbons) | Soil |
PHCs (petroleum hydrocarbons) | Air |
BTEXs (benzene, toluene, ethylbenzene, and xylene) | Groundwater |
BTEXs (benzene, toluene, ethylbenzene, and xylene) | Soil |
BTEXs (benzene, toluene, ethylbenzene, and xylene) | Air |
PAHs (polycyclic aromatic hydrocarbon) | Groundwater |
PAHs (polycyclic aromatic hydrocarbon) | Soil |
PAHs (polycyclic aromatic hydrocarbon) | Air |
Metal, metalloid, and organometallic | Groundwater |
Metal, metalloid, and organometallic | Soil |
Action Plan
Site is under assessment steps.
Additional Information
The site is located in a National Park of Canada.
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 0 |
5 km | 176 |
10 km | 592 |
25 km | 2,624 |
50 km | 12,323 |
Summary of Annually Reported Data
Total Expenditures
-
Assessment
$226,533.00 -
Remediation
$998,968.82 -
Monitoring
$102,600.00
FCSAP Expenditures
-
Assessment
$182,688.00 -
Remediation
$997,643.82 -
Monitoring
$101,275.00
Financial/Annual Information
2023-2024click to collapse contents
2023-2024
Reporting Organization
Parks Canada AgencyInternal Identifier
TWPRMNT012Highest Step Completed
09 Confirmatory Sampling and Final ReportingTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
- Version:
- 42