Site 00025801 - Institute for Biodiagnostics, Winnipeg
-
Status
Initial testing completed. No further action required. -
Site Status
Closed -
Classification
Site Details
-
Reporting Organization
-
Reason for Involvement
Federal Real Property -
Property Type
Federal (DFRP Property Number 30921)
Site Location
-
Latitude, Longitude
49.894234, -97.15061 -
Municipality
Winnipeg, MB -
Federal Electoral District
Winnipeg Centre
Site Management Strategy
- Assessment
Action Plan
No further action required. A preliminary environmental site investigation (Phase II Environmental Site Assessment) was completed in summer/fall 2013 to assess the areas of potential concern. No further action was required, and as such the site file was closed. The site will continue to be used for research.
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 21,799 |
5 km | 234,739 |
10 km | 586,040 |
25 km | 768,545 |
50 km | 852,873 |
Summary of Annually Reported Data
Total Expenditures
-
Assessment
$31,537.00
FCSAP Expenditures
-
Assessment
$24,121.00
Financial/Annual Information
2015-2016click to collapse contents
2015-2016
Reporting Organization
National Research Council CanadaInternal Identifier
NRC - IBD WinnipegHighest Step Completed
03 Initial Testing ProgramTotal Assessment Expenditure
$7,416.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed