Site 00027593 - Technical and Protective Operations Facility (TPOF)
-
Status
Remediation / risk management completed. No further action required. -
Site Status
Closed -
Classification
High Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
Federal Real Property -
Property Type
Federal (DFRP Property Number 08533)
Site Location
-
Latitude, Longitude
45.451928, -75.558483 -
Municipality
Ottawa, ON -
Federal Electoral District
Orléans
Site Management Strategy
- Assessment
Contaminant Details
Contamination Estimate
-
Cubic Meters
13,000 -
Hectares
2
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
PHCs (petroleum hydrocarbons) | Surface water |
PHCs (petroleum hydrocarbons) | Groundwater |
PHCs (petroleum hydrocarbons) | Sediment |
PHCs (petroleum hydrocarbons) | Soil |
BTEXs (benzene, toluene, ethylbenzene, and xylene) | Soil |
PAHs (polycyclic aromatic hydrocarbon) | Surface water |
PAHs (polycyclic aromatic hydrocarbon) | Groundwater |
PAHs (polycyclic aromatic hydrocarbon) | Sediment |
PAHs (polycyclic aromatic hydrocarbon) | Soil |
Metal, metalloid, and organometallic | Surface water |
Metal, metalloid, and organometallic | Groundwater |
Metal, metalloid, and organometallic | Sediment |
Metal, metalloid, and organometallic | Soil |
Other Physical/Chemical (pH, temperature, dissolved solids, turbidity, etc.) | Surface water |
Other Physical/Chemical (pH, temperature, dissolved solids, turbidity, etc.) | Sediment |
Action Plan
A detailed environmental site assessment will be completed in 2021-2022.
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 240 |
5 km | 90,755 |
10 km | 332,698 |
25 km | 1,081,598 |
50 km | 1,417,146 |
Summary of Annually Reported Data
Total Expenditures
-
Assessment
$668,580.78 -
Remediation
$19,761.24
Financial/Annual Information
2021-2022click to collapse contents
2021-2022
Reporting Organization
Royal Canadian Mounted PoliceInternal Identifier
PR N/10Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$96,250.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
Yes
- Version:
- 42