Site 05042021 - 688 - Tk'emlúps te Secwépemc - 07173 - KAMLOOPS 1 - 7000070696

  • Status

    Remediation / risk management completed. Confirmatory sampling underway.
  • Site Status

    Active
  • Classification

    Medium Priority for Action

Site Details

  • Reporting Organization

  • Reason for Involvement

    A reserve as defined in the Indian Act
  • Property Type

    Canada Lands

Site Location

Locate this site on map
  • Latitude, Longitude

    50.714018, -120.31235
  • Municipality

    Kamloops 1, BC
  • Federal Electoral District

    Kamloops--Thompson--Cariboo

Site Management Strategy

  • Remediation

Contaminant Details

Contamination Estimate

  • Cubic Meters

    17,000
  • Hectares

    5

The following contaminated media was identified on the site:

Contaminant Type Medium Type
PHCs (petroleum hydrocarbons) Surface soil
PHCs (petroleum hydrocarbons) Soil
BTEXs (benzene, toluene, ethylbenzene, and xylene) Surface soil
BTEXs (benzene, toluene, ethylbenzene, and xylene) Soil
PAHs (polycyclic aromatic hydrocarbon) Surface soil
PAHs (polycyclic aromatic hydrocarbon) Soil
Metal, metalloid, and organometallic Surface soil
Metal, metalloid, and organometallic Soil
PCBs (Polychlorinated Biphenyl) and PCDD/Fs (polychlorinated dibenzo-p-dioxin/dibenzofuran) Surface soil
PCBs (Polychlorinated Biphenyl) and PCDD/Fs (polychlorinated dibenzo-p-dioxin/dibenzofuran) Soil
Other inorganics Surface soil
Other inorganics Soil
Other organics Surface soil
Other organics Soil

Population

This table contains the population estimates at distances around the site.

Radius Population
1 km9
5 km33,071
10 km86,220
25 km102,229
50 km113,870

Summary of Annually Reported Data

Total Expenditures

  • Assessment

    $12,066.08
  • Remediation

    $4,897,242.00

FCSAP Expenditures

  • Assessment

    $9,652.86
  • Remediation

    $4,092,050.00

Financial/Annual Information

2023-2024click to collapse contents 

2023-2024

  • Reporting Organization

    Indigenous Services Canada
  • Internal Identifier

    7000070696
  • Highest Step Completed

    08 Implement Remediation/Risk Management Strategy
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2022-2023click to expand contents 

2021-2022click to expand contents 

2020-2021click to expand contents 

2019-2020click to expand contents 

2019-2020click to expand contents 

2018-2019click to expand contents 

2017-2018click to expand contents 

2016-2017click to expand contents 

2015-2016click to expand contents 

2014-2015click to expand contents 

2013-2014click to expand contents 

2012-2013click to expand contents 

2011-2012click to expand contents 

2010-2011click to expand contents 

2009-2010click to expand contents 

2008-2009click to expand contents 

2007-2008click to expand contents 

2006-2007click to expand contents 

2005-2006click to expand contents 

 

loading