Site 09401220 - Alaska Highway - Sikanni Chief NWSC Camp (quarry) I-20
-
Status
Remedial action plan completed. Remediation / risk management underway. -
Site Status
Active -
Classification
High Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
Contractual obligation -
Property Type
Non-Federal (Provincial Government)
Site Location
-
Latitude, Longitude
57.241666, -122.71111 -
Municipality
Peace River B, BC -
Federal Electoral District
Prince George--Peace River--Northern Rockies
Site Management Strategy
- Additional assessment
Contaminant Details
Contamination Estimate
-
Cubic Meters
1,000
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
PHCs (petroleum hydrocarbons) | Surface soil |
PHCs (petroleum hydrocarbons) | Soil |
BTEXs (benzene, toluene, ethylbenzene, and xylene) | Surface soil |
BTEXs (benzene, toluene, ethylbenzene, and xylene) | Soil |
PAHs (polycyclic aromatic hydrocarbon) | Surface soil |
PAHs (polycyclic aromatic hydrocarbon) | Soil |
Metal, metalloid, and organometallic | Surface soil |
Metal, metalloid, and organometallic | Soil |
Action Plan
Excavation of Hydrocarbon Contaminated Soil and off site disposal of Soil; Risk Assessment of Metals Contaminated Groundwater. Risk assessment conducted in 2016-2017 found unnacceptable risk.
Additional Information
Excavation of Hydrocarbon Contaminated Soil and off site disposal of Soil; Risk Assessment of Metals Contaminated Groundwater.
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 0 |
5 km | 5 |
10 km | 20 |
25 km | 108 |
50 km | 369 |
Summary of Annually Reported Data
Total Expenditures
-
Remediation
$463,587.83
FCSAP Expenditures
-
Remediation
$463,587.83
Financial/Annual Information
2023-2024click to collapse contents
2023-2024
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Pacific 09401220Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed