Site 10855002 - London Airport - Former Firefighting Training Areas
-
Status
Confirmatory sampling completed. Long term monitoring underway. -
Site Status
Active -
Classification
High Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
Federal Real Property -
Property Type
Federal (DFRP Property Number 10855)
Site Location
-
Latitude, Longitude
43.031323, -81.162279 -
Municipality
London, ON -
Federal Electoral District
London--Fanshawe
Site Management Strategy
- Continous Monitoring
Contaminant Details
Contamination Estimate
-
Hectares
15
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
PHCs (petroleum hydrocarbons) | Groundwater |
PHCs (petroleum hydrocarbons) | Sediment |
PHCs (petroleum hydrocarbons) | Soil |
BTEXs (benzene, toluene, ethylbenzene, and xylene) | Groundwater |
BTEXs (benzene, toluene, ethylbenzene, and xylene) | Soil |
PAHs (polycyclic aromatic hydrocarbon) | Groundwater |
PAHs (polycyclic aromatic hydrocarbon) | Sediment |
PAHs (polycyclic aromatic hydrocarbon) | Soil |
Metal, metalloid, and organometallic | Groundwater |
Metal, metalloid, and organometallic | Soil |
PFAS (per and poly fluoroalkyl substances) | Groundwater |
Other organics | Surface water |
Other organics | Groundwater |
Other organics | Sediment |
Other organics | Soil |
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 87 |
5 km | 44,133 |
10 km | 196,055 |
25 km | 444,999 |
50 km | 720,176 |
Summary of Annually Reported Data
Total Expenditures
-
Assessment
$215,983.51 -
Remediation
$1,834,810.02
FCSAP Expenditures
-
Assessment
$214,985.89 -
Remediation
$1,559,588.43
Financial/Annual Information
2023-2024click to collapse contents
2023-2024
Reporting Organization
Transport CanadaInternal Identifier
10855002Highest Step Completed
09 Confirmatory Sampling and Final ReportingTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$95,773.56Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$81,407.53FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
- Version:
- 42