Site 11022158 - Circled Pine Maint. Shed, B O-138: Fuel Storage & Septic bed

  • Status

    Initial testing completed. No further action required.
  • Site Status

    Closed
  • Classification

Site Details

  • Reporting Organization

  • Reason for Involvement

    Federal Real Property
  • Property Type

    Federal (DFRP Property Number 11022)

Site Location

Locate this site on map
  • Latitude, Longitude

    44.2965, -79.8769
  • Municipality

    Essa, ON
  • Federal Electoral District

    Simcoe--Grey

Site Management Strategy

  • Assessment

Contaminant Details

Contamination Estimate

The following contaminated media may exist on the site:

Contaminant Type Medium Type
PHCs (petroleum hydrocarbons) Surface water
PHCs (petroleum hydrocarbons) Groundwater
PHCs (petroleum hydrocarbons) Soil
Metal, metalloid, and organometallic Surface water
Metal, metalloid, and organometallic Groundwater
Metal, metalloid, and organometallic Soil
Other Physical/Chemical (pH, temperature, dissolved solids, turbidity, etc.) Surface water
Other Physical/Chemical (pH, temperature, dissolved solids, turbidity, etc.) Groundwater
Other Physical/Chemical (pH, temperature, dissolved solids, turbidity, etc.) Soil

Population

This table contains the population estimates at distances around the site.

Radius Population
1 km805
5 km13,542
10 km19,683
25 km255,798
50 km1,093,291

Summary of Annually Reported Data

Total Expenditures

  • Assessment

    $51,629.10

FCSAP Expenditures

  • Assessment

    $10,270.40

Financial/Annual Information

2010-2011click to collapse contents 

2010-2011

  • Reporting Organization

    National Defence
  • Internal Identifier

    S10477
  • Highest Step Completed

    03 Initial Testing Program
  • Total Assessment Expenditure

    $38,791.10
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    Yes

2009-2010click to expand contents 

2008-2009click to expand contents 

2007-2008click to expand contents 

2006-2007click to expand contents 

2005-2006click to expand contents 

 

loading