Site 12738001 - Fire Training Area

  • Status

    Detailed testing completed. No further action required.
  • Site Status

    Closed
  • Classification

    Medium Priority for Action

Site Details

  • Reporting Organization

  • Reason for Involvement

    Federal Real Property
  • Property Type

    Federal (DFRP Property Number 12738)

Site Location

Locate this site on map
  • Latitude, Longitude

    49.919279, -97.248814
  • Municipality

    Rosser, MB
  • Federal Electoral District

    Selkirk--Interlake--Eastman

Contaminant Details

Contamination Estimate

  • Cubic Meters

    16,000
  • Hectares

    1

The following contaminated media was identified on the site:

Contaminant Type Medium Type
PHCs (petroleum hydrocarbons) Not Available
BTEXs (benzene, toluene, ethylbenzene, and xylene) Soil
PAHs (polycyclic aromatic hydrocarbon) Not Available

Action Plan

2018/2019 No work completed at the site in regards to the known Contaminants of Concern. A new site in the same location has been created for PFAS impact at the site as assessment for PFAS is ongoing and at a different FCSAP step.

Additional Information

Further Assessment on-going. Site has been split into two under CSMD with the second for PFAS contamination. The two sites in the same location are at two different steps in the 10 step process, as assessment is ongoing for PFAS.

Population

This table contains the population estimates at distances around the site.

Radius Population
1 km22
5 km62,631
10 km367,342
25 km759,199
50 km839,103

Summary of Annually Reported Data

Total Expenditures

  • Assessment

    $99,193.97
  • Remediation

    $8,954.25

Financial/Annual Information

2023-2024click to collapse contents 

2023-2024

  • Reporting Organization

    Transport Canada
  • Internal Identifier

    12738001
  • Highest Step Completed

    07 Develop Remediation/Risk Management Strategy
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    Yes

2022-2023click to expand contents 

2021-2022click to expand contents 

2020-2021click to expand contents 

2019-2020click to expand contents 

2018-2019click to expand contents 

2017-2018click to expand contents 

2016-2017click to expand contents 

2015-2016click to expand contents 

2014-2015click to expand contents 

2013-2014click to expand contents 

2012-2013click to expand contents 

2011-2012click to expand contents 

2010-2011click to expand contents 

2009-2010click to expand contents 

2008-2009click to expand contents 

2007-2008click to expand contents 

2006-2007click to expand contents 

2005-2006click to expand contents 

 

loading