Site 15412017 - C2 JNP Tangle Creek Compound
-
Status
Remedial action plan completed. Remediation / risk management underway. -
Site Status
Active -
Classification
Medium Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
National Park of Canada -
Property Type
Canada Lands
Site Location
-
Latitude, Longitude
52.2664, -117.2924 -
Municipality
Improvement District No. 12 Jasper Park, AB -
Federal Electoral District
Yellowhead
Site Management Strategy
- Periodic Monitoring
- Additional assessment
Contaminant Details
Contamination Estimate
-
Cubic Meters
895
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
PHCs (petroleum hydrocarbons) | Soil |
BTEXs (benzene, toluene, ethylbenzene, and xylene) | Soil |
Metal, metalloid, and organometallic | Groundwater |
Other organics | Groundwater |
Action Plan
Site is under remediation and/or risk management steps.
Additional Information
The site is located in a National Park of Canada.
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 0 |
5 km | 0 |
10 km | 0 |
25 km | 31 |
50 km | 355 |
Summary of Annually Reported Data
Total Expenditures
-
Assessment
$184,063.00 -
Remediation
$579,797.50
FCSAP Expenditures
-
Assessment
$47,781.00 -
Remediation
$435,460.50
Financial/Annual Information
2023-2024click to collapse contents
2023-2024
Reporting Organization
Parks Canada AgencyInternal Identifier
AWPJAST017Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$79,176.78Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$75,079.78FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
- Version:
- 42