Site 23148001 - Contrecoeur landfill

  • Status

    Remediation / risk management completed. Confirmatory sampling underway.
  • Site Status

    Active
  • Classification

    High Priority for Action

Site Details

Site Location

Locate this site on map
  • Latitude, Longitude

    45.86222, -73.19555
  • Municipality

    Contrecoeur, QC
  • Federal Electoral District

    Pierre-Boucher--Les Patriotes--Verchères

Site Management Strategy

  • Other

Contaminant Details

Contamination Estimate

  • Hectares

    5

The following contaminated media was identified on the site:

Contaminant Type Medium Type
PHCs (petroleum hydrocarbons) Surface water
PHCs (petroleum hydrocarbons) Groundwater
PHCs (petroleum hydrocarbons) Surface soil
PHCs (petroleum hydrocarbons) Soil
PAHs (polycyclic aromatic hydrocarbon) Surface water
PAHs (polycyclic aromatic hydrocarbon) Groundwater
PAHs (polycyclic aromatic hydrocarbon) Surface soil
PAHs (polycyclic aromatic hydrocarbon) Soil
Metal, metalloid, and organometallic Surface water
Metal, metalloid, and organometallic Groundwater
Metal, metalloid, and organometallic Surface soil
Metal, metalloid, and organometallic Soil
PCBs (Polychlorinated Biphenyl) and PCDD/Fs (polychlorinated dibenzo-p-dioxin/dibenzofuran) Surface water
PCBs (Polychlorinated Biphenyl) and PCDD/Fs (polychlorinated dibenzo-p-dioxin/dibenzofuran) Groundwater
PCBs (Polychlorinated Biphenyl) and PCDD/Fs (polychlorinated dibenzo-p-dioxin/dibenzofuran) Surface soil
PCBs (Polychlorinated Biphenyl) and PCDD/Fs (polychlorinated dibenzo-p-dioxin/dibenzofuran) Soil
Other Physical/Chemical (pH, temperature, dissolved solids, turbidity, etc.) Surface water
Other Physical/Chemical (pH, temperature, dissolved solids, turbidity, etc.) Groundwater
Other Physical/Chemical (pH, temperature, dissolved solids, turbidity, etc.) Surface soil
Other Physical/Chemical (pH, temperature, dissolved solids, turbidity, etc.) Soil

Action Plan

Management/remediation plan finalized based on a risk analysis. Remediation/management plan implentation has begun in 2019-2020 and will be finished in 2021-2022.

Population

This table contains the population estimates at distances around the site.

Radius Population
1 km157
5 km9,311
10 km36,720
25 km272,426
50 km2,441,178

Summary of Annually Reported Data

Total Expenditures

  • Assessment

    $386,767.49
  • Remediation

    $6,935,384.66

FCSAP Expenditures

  • Assessment

    $347,102.29
  • Remediation

    $5,894,141.62

Financial/Annual Information

2023-2024click to collapse contents 

2023-2024

  • Reporting Organization

    Public Services and Procurement Canada
  • Internal Identifier

    Quebec 23148001
  • Highest Step Completed

    08 Implement Remediation/Risk Management Strategy
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $110,656.07
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $94,057.66
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2022-2023click to expand contents 

2021-2022click to expand contents 

2020-2021click to expand contents 

2019-2020click to expand contents 

2018-2019click to expand contents 

2017-2018click to expand contents 

2016-2017click to expand contents 

2015-2016click to expand contents 

 

loading