Site 29793001 - Former Red Route Dump East Site
-
Status
Detailed testing completed. Remediation / risk management planned. -
Site Status
Active -
Classification
Medium Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
Federal Real Property -
Property Type
Federal (DFRP Property Number 15304)
Site Location
-
Latitude, Longitude
52.8175, -110.941 -
Municipality
Wainwright No. 61, AB -
Federal Electoral District
Battle River--Crowfoot
Site Management Strategy
- Periodic Monitoring
Contaminant Details
Contamination Estimate
-
Hectares
8
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
BTEXs (benzene, toluene, ethylbenzene, and xylene) | Groundwater |
Metal, metalloid, and organometallic | Groundwater |
PCBs (Polychlorinated Biphenyl) and PCDD/Fs (polychlorinated dibenzo-p-dioxin/dibenzofuran) | Groundwater |
Pesticides | Groundwater |
Other inorganics | Groundwater |
Other organics | Groundwater |
Other Physical/Chemical (pH, temperature, dissolved solids, turbidity, etc.) | Groundwater |
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 27 |
5 km | 776 |
10 km | 7,282 |
25 km | 9,693 |
50 km | 16,386 |
Summary of Annually Reported Data
Total Expenditures
-
Assessment
$22,719.31 -
Remediation
$7,421.77
FCSAP Expenditures
-
Assessment
$12,200.00
Financial/Annual Information
2023-2024click to collapse contents
2023-2024
Reporting Organization
National DefenceInternal Identifier
0465-C022Highest Step Completed
05 Detailed Testing ProgramTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed