Site 53720001 - Former Selkirk Shipyard
-
Status
Detailed testing completed. No further action required. -
Site Status
Closed -
Classification
High Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
Contractual obligation -
Property Type
Non-Federal (Private Sector)
Site Location
-
Latitude, Longitude
50.152923, -96.864451 -
Municipality
Selkirk, MB -
Federal Electoral District
Selkirk--Interlake--Eastman
Site Management Strategy
- Remediation
Contaminant Details
Contamination Estimate
-
Cubic Meters
4,505
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
PHCs (petroleum hydrocarbons) | Groundwater |
PHCs (petroleum hydrocarbons) | Soil |
PAHs (polycyclic aromatic hydrocarbon) | Groundwater |
PAHs (polycyclic aromatic hydrocarbon) | Soil |
Metal, metalloid, and organometallic | Groundwater |
Metal, metalloid, and organometallic | Soil |
Action Plan
In 2008/09 the groundwater in two monitoring wells still exceeded criteria. A Preliminary Quantitative Risk Assessment (PQRA) was conducted in 2009/10. Contaminated groundwater and soil were monitored and data gaps were identified and sampled for FY 2011/2012. Remedial options were developed in FY 2012/2013. A remedial plan will be developed in 2013/2014. RPS is seeking a legal opinion on whether cleanup is required prior to divestiture of the site. In 2013-2014, RPS AFMS is pursuing divestiture of the site. No work completed in 2014-2015. Property divested in 2015-16.
Additional Information
Site has been reclassified as Class 1 this fiscal year based on additional assessment. Site is near the location of former fuel storage tanks, to the east of the machine shop & PAH-contaminated soils near the rail tracks and coal storage pile
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 1,586 |
5 km | 12,486 |
10 km | 16,986 |
25 km | 57,337 |
50 km | 826,052 |
Summary of Annually Reported Data
Total Expenditures
-
Assessment
$41,313.94 -
Remediation
$155,800.12 -
Care & Maintenance
$3,295.00
FCSAP Expenditures
-
Assessment
$19,950.75
Financial/Annual Information
2015-2016
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Western 53720001Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
Yes
2014-2015
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Western 53720001Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2013-2014
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Western 53720001Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2012-2013
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Western 53720001Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$95,800.12Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2011-2012
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Western 53720001Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$60,000.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2010-2011
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Western 53720001Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2009-2010
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Western 53720001Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$31,541.87Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$19,950.75FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2008-2009
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Western 53720001Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$2,436.33Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2007-2008
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Western 53720001Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$3,335.74Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2006-2007
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Western 53720001Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$3,295.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2005-2006
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Western 53720001Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$4,000.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed