Site 55793006 - Southside Landfill # 1 (SLF1)
-
Status
Long term monitoring completed. No further action required. -
Site Status
Closed -
Classification
Medium Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
Contractual obligation -
Property Type
Non-Federal (Private Sector)
Site Location
-
Latitude, Longitude
47.2825, -54.0035 -
Municipality
Division No. 1, Subd. B, NL -
Federal Electoral District
Avalon
Site Management Strategy
- Periodic Monitoring
Contaminant Details
Contamination Estimate
-
Cubic Meters
350,000
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
PHCs (petroleum hydrocarbons) | Groundwater |
PHCs (petroleum hydrocarbons) | Soil |
PAHs (polycyclic aromatic hydrocarbon) | Groundwater |
PAHs (polycyclic aromatic hydrocarbon) | Soil |
Metal, metalloid, and organometallic | Groundwater |
Metal, metalloid, and organometallic | Soil |
Other organics | Groundwater |
Other organics | Soil |
Action Plan
Groundwater and leachate monitoring ongoing.
Additional Information
Concrete barrier wall has been installed.
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 27 |
5 km | 1,095 |
10 km | 3,189 |
25 km | 5,334 |
50 km | 19,731 |
Summary of Annually Reported Data
Total Expenditures
-
Assessment
$80,981.31 -
Remediation
$419,686.24
Financial/Annual Information
- 2023-2024
- 2022-2023
- 2021-2022
- 2020-2021
- 2019-2020
- 2018-2019
- 2017-2018
- 2016-2017
- 2015-2016
- 2014-2015
- 2013-2014
- 2012-2013
- 2011-2012
- 2010-2011
- 2009-2010
- 2008-2009
- 2007-2008
- 2006-2007
- 2005-2006
2023-2024
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Atlantic 55793006Highest Step Completed
10 Long-Term Monitoring (Optional)Total Assessment Expenditure
$0.00Total Remediation Expenditure
$21,554.97Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2022-2023
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Atlantic 55793006Highest Step Completed
10 Long-Term Monitoring (Optional)Total Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2021-2022
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Atlantic 55793006Highest Step Completed
10 Long-Term Monitoring (Optional)Total Assessment Expenditure
$0.00Total Remediation Expenditure
$21,603.30Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2020-2021
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Atlantic 55793006Highest Step Completed
10 Long-Term Monitoring (Optional)Total Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2019-2020
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Atlantic 55793006Highest Step Completed
10 Long-Term Monitoring (Optional)Total Assessment Expenditure
$0.00Total Remediation Expenditure
$16,848.51Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2018-2019
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Atlantic 55793006Highest Step Completed
10 Long-Term Monitoring (Optional)Total Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2017-2018
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Atlantic 55793006Highest Step Completed
10 Long-Term Monitoring (Optional)Total Assessment Expenditure
$0.00Total Remediation Expenditure
$13,412.64Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2016-2017
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Atlantic 55793006Highest Step Completed
10 Long-Term Monitoring (Optional)Total Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2015-2016
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Atlantic 55793006Highest Step Completed
10 Long-Term Monitoring (Optional)Total Assessment Expenditure
$0.00Total Remediation Expenditure
$12,259.83Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2014-2015
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Atlantic 55793006Highest Step Completed
10 Long-Term Monitoring (Optional)Total Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2013-2014
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Atlantic 55793006Highest Step Completed
10 Long-Term Monitoring (Optional)Total Assessment Expenditure
$0.00Total Remediation Expenditure
$19,121.48Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2012-2013
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Atlantic 55793006Highest Step Completed
10 Long-Term Monitoring (Optional)Total Assessment Expenditure
$0.00Total Remediation Expenditure
$2,795.17Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2011-2012
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Atlantic 55793006Highest Step Completed
10 Long-Term Monitoring (Optional)Total Assessment Expenditure
$38,105.94Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2010-2011
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Atlantic 55793006Highest Step Completed
09 Confirmatory Sampling and Final ReportingTotal Assessment Expenditure
$22,512.97Total Remediation Expenditure
$2,841.31Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2009-2010
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Atlantic 55793006Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$6,687.87Total Remediation Expenditure
$275,556.42Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2008-2009
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Atlantic 55793006Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$33,692.61Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2007-2008
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Atlantic 55793006Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$5,457.78Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2006-2007
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Atlantic 55793006Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$2,164.75Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2005-2006
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Atlantic 55793006Highest Step Completed
06 Classify the site using the CCME National Classification SystemTotal Assessment Expenditure
$6,052.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
- Version:
- 42