Site 55793020 - Temporary hydrocarbon contaminated soil containment facility. (Soil Berm)
-
Status
Confirmatory sampling completed. No further action required. -
Site Status
Closed -
Classification
Medium Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
Contractual obligation -
Property Type
Non-Federal (Private Sector)
Site Location
-
Latitude, Longitude
47.3167, -54.0014 -
Municipality
Placentia, NL -
Federal Electoral District
Avalon
Contaminant Details
Contamination Estimate
-
Tons
11,000
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
PHCs (petroleum hydrocarbons) | Soil |
PAHs (polycyclic aromatic hydrocarbon) | Soil |
Other organics | Soil |
Action Plan
Soil has been disposed of on-site according to contamination level. Heavily impacted soil was transported and capped at the Secure Landfill and less impacted soil was placed under the cap at SLF1.
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 25 |
5 km | 297 |
10 km | 2,896 |
25 km | 5,135 |
50 km | 21,042 |
Summary of Annually Reported Data
Total Expenditures
-
Assessment
$219,952.04 -
Remediation
$3,671,673.91
Financial/Annual Information
2011-2012
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Atlantic 55793020Highest Step Completed
09 Confirmatory Sampling and Final ReportingTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
10000 tClosed
Yes
2010-2011
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Atlantic 55793020Highest Step Completed
09 Confirmatory Sampling and Final ReportingTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
10000 tClosed
Yes
2009-2010
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Atlantic 55793020Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$11,103.04Total Remediation Expenditure
$1,796,702.91Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
10000 tClosed
No
2008-2009
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Atlantic 55793020Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$1,324,943.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
10000 tClosed
No
2007-2008
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Atlantic 55793020Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$83,635.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2006-2007
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Atlantic 55793020Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$125,214.00Total Remediation Expenditure
$134,751.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2005-2006
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Atlantic 55793020Highest Step Completed
06 Classify the site using the CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$415,277.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
- Version:
- 42