Search Results
Search Results Summary | |
---|---|
Criteria: |
|
Sort Key: | Country (ascending) |
Sites Found: | 15 |
Results by Site Impact
Change results view to: Name and Location Contaminants and Media
FCSI Identifier Site Name |
Status | Fiscal Year | Classification | Highest Step Completed |
---|---|---|---|---|
00012549
BROWNSDALE (Waterlot) |
Initial testing completed. No further action required. | 2008-2009 | N Not a Priority for Action | 03 Initial Testing Program |
00012585
New Chelsea (Wharf Site - DFRP# 00165 - Upland and |
Initial testing completed. No further action required. | 2021-2022 | 03 Initial Testing Program | |
00018334
Hants Harbour (Breakwater - Unassessed) |
Historical review not required. | 2009-2010 | 01 Identify Suspect Sites | |
00018557
Sibley's Cove |
Historical review completed. No further action required. | 2012-2013 | 02 Historical Review | |
00019124
Hant's Harbour (Road Site - Waterlot - DFRP# 34510) |
Initial testing completed. Detailed testing underway. | 2023-2024 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00019125
Hant's Harbour (Custers Road Slipway Site - Uplands - DFRP# 55925 & 55926) |
Initial testing completed. No further action required. | 2008-2009 | N Not a Priority for Action | 03 Initial Testing Program |
00019228
New Perlican (Unassessed) |
Historical review completed. No further action required. | 2023-2024 | 02 Historical Review | |
00019322
Sibley's Cove (SCH - Uplands - DFRP# 00167) |
Detailed testing completed. No further action required. | 2012-2013 | N Not a Priority for Action | 06 Classify the site using the CCME National Classification System |
00019323
Sibley's Cove (SCH - Waterlot - DFRP# 00167) |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | N Not a Priority for Action | 06 Classify the site using the CCME National Classification System |
00022962
New Chelsea (Slipway - DFRP# 23856 - Waterlot) |
Initial testing completed. No further action required. | 2021-2022 | 03 Initial Testing Program | |
00022963
New Chelsea (Slipway - DFRP# 23856 - Uplands) |
Detailed testing completed. No further action required. | 2021-2022 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00023033
Hant's Harbour (L-Shaped Finger Pier Site - Waterlot -DFRP#00181) |
Initial testing completed. Detailed testing underway. | 2023-2024 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00023034
Breakwater site (Uplands - DFRP# 34512) |
Initial testing completed. No further action required. | 2008-2009 | N Not a Priority for Action | 03 Initial Testing Program |
00023035
Hant's Harbour (Road Site - Uplands - DFRP#34510) |
Initial testing completed. Detailed testing underway. | 2023-2024 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00023036
Hant's Harbour (L-Shaped Finger Pier Site - Uplands -DFRP#00181) |
Initial testing completed. No further action required. | 2008-2009 | N Not a Priority for Action | 03 Initial Testing Program |
- Version:
- 40