Status | Fiscal Year | Classification | Highest Step Completed |
---|---|---|---|---|
00012569
BARR'D ISLANDS (Uplands and Waterlot) |
Historical review completed. No further action required. | 2008-2009 | N Not a Priority for Action | 02 Historical Review |
00013141
Seldom Come By (In-Filled Area) |
Detailed testing completed. No further action required. | 2012-2013 | N Not a Priority for Action | 06 Classify the site using the CCME National Classification System |
00018134
Barr'd Island - Minor Aid |
Initial testing completed. No further action required. | 2016-2017 | 03 Initial Testing Program | |
00018181
Cann Island - Seldom Cove - Minor Aid |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 3 Low Priority for Action | 06 Classify the site using the CCME National Classification System |
00018266
Fogo (Unassessed) |
Historical review completed. No further action required. | 2016-2017 | 02 Historical Review | |
00018267
Fogo Island - Front Range |
Initial testing completed. No further action required. | 2012-2013 | 03 Initial Testing Program | |
00018268
Fogo Island - Rear Range |
Initial testing completed. No further action required. | 2012-2013 | 03 Initial Testing Program | |
00018371
Joe Batts Arm |
Historical review not required. | 2012-2013 | 01 Identify Suspect Sites | |
00018372
Joe Batts Arm (Wharf) |
Historical review completed. No further action required. | 2008-2009 | 02 Historical Review | |
00018373
Joe Batt's Point - Minor Aid |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 3 Low Priority for Action | 08 Implement Remediation/Risk Management Strategy |
00018397
Little Fogo Island - Minor Aid |
Detailed testing completed. No further action required. | 2008-2009 | 3 Low Priority for Action | 05 Detailed Testing Program |
00018425
Man O'War Cove - Unassessed |
Historical review not required. | 2012-2013 | 01 Identify Suspect Sites | |
00018438
Middle Rock - Minor Aid |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
00018517
Rags Island - Minor Aid |
Detailed testing completed. No further action required. | 2014-2015 | N Not a Priority for Action | 05 Detailed Testing Program |
00018549
Seal Cove (Wharf) |
Historical review completed. No further action required. | 2012-2013 | 02 Historical Review | |
00018619
Storehouse Island - Minor Aid |
Detailed testing completed. No further action required. | 2008-2009 | 3 Low Priority for Action | 05 Detailed Testing Program |
00018628
Tilting Harbour - Minor Aid |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
00018629
Tinker Rock - Minor Aid |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
00018715
Seldom (Wharf Light) |
Historical review completed. No further action required. | 2012-2013 | 02 Historical Review | |
00018734
Barracks Island |
Historical review completed. No further action required. | 2008-2009 | 02 Historical Review | |
00018735
Gappy Island - Unassessed |
Historical review completed. No further action required. | 2016-2017 | 02 Historical Review | |
00018792
Fogo (VHF - Unassessed) |
Historical review not required. | 2012-2013 | 01 Identify Suspect Sites | |
00018808
Man O War Cove - Dolphin - Unassessed |
Historical review not required. | 2012-2013 | 01 Identify Suspect Sites | |
00018961
Tilting (Fuel Oil Storage Depot) |
Detailed testing completed. No further action required. | 2014-2015 | I Insufficient Information | 05 Detailed Testing Program |
00019096
Fogo (SCH - Wigwam Point - Waterlot - DFRP# 01356) |
Detailed testing completed. No further action required. | 2021-2022 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00019162
Joe Batt's Arm (East Waterlot - DFRP# 01365) |
Initial testing completed. No further action required. | 2012-2013 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00019163
Joe Batt's Arm (West Waterlot - DFRP# 01337) |
Initial testing completed. No further action required. | 2012-2013 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00019164
Joe Batt's Arm (East Uplands - DFRP# 01365) |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 3 Low Priority for Action | 06 Classify the site using the CCME National Classification System |
00019165
Joe Batt's Arm (West Uplands - DFRP# 01337) |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 3 Low Priority for Action | 06 Classify the site using the CCME National Classification System |
00019313
Seldom Come By (Uplands - DFRP# 01336) |
Detailed testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00019360
Stag Harbour (SCH - Uplands - DFRP# 01338) |
Initial testing completed. No further action required. | 2012-2013 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00019361
Stag Harbour (SCH - Waterlot - DFRP# 01338) |
Initial testing completed. No further action required. | 2012-2013 | 03 Initial Testing Program | |
00019372
Tilting (Fingerpier/ wharf - Uplands - 01371) |
Detailed testing completed. No further action required. | 2008-2009 | N Not a Priority for Action | 05 Detailed Testing Program |
00024358
Fogo (SCH - Wigwam Point - Uplands - DFRP# 01356) |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00024359
Fogo (SCH - Canal Site - Waterlot - DFRP# 01358) |
Initial testing completed. No further action required. | 2012-2013 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00024360
Fogo (SCH - Canal Site - Uplands - DFRP# 01358) |
Detailed testing completed. No further action required. | 2020-2021 | 2 Medium Priority for Action | 05 Detailed Testing Program |
00025401
Barr'd Islands (DFRP 01364 Uplands) |
Initial testing completed. Detailed testing underway. | 2023-2024 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
01333001
Seldom Come By (South - Uplands - DFRP# 01333) |
Detailed testing completed. No further action required. | 2023-2024 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
01333002
Seldom Come By (South - Waterlot - DFRP# 01333) |
Detailed testing completed. No further action required. | 2018-2019 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
01333003
Seldom Come By (Waterlot - DFRP # 01336) |
Detailed testing completed. No further action required. | 2012-2013 | N Not a Priority for Action | 07 Develop Remediation/Risk Management Strategy |
01334001
Deep Bay (Uplands Property) |
Detailed testing completed. No further action required. | 2014-2015 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
01334002
Deep Bay (Waterlot Property) |
Detailed testing completed. No further action required. | 2021-2022 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
01371001
Tilting (Fish Plant Wharf - Uplands - 34639) |
Detailed testing completed. No further action required. | 2021-2022 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
01371002
Tilting (Fish Plant facility - Waterlot - 34639) |
Detailed testing completed. No further action required. | 2021-2022 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
01371003
Tilting (Fingerpier/Wharf - Waterlot - 01371) |
Detailed testing completed. No further action required. | 2021-2022 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
34931001
Burnt Point - Lightstation - DFRP# 34391 |
Confirmatory sampling completed. No further action required. | 2012-2013 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |