Search Results

Search Results Summary
Criteria:
  • Census Subdivision: Sudbury, Unorganized, North Part
Select Additional Criteria...
Sort Key:Site Name (ascending)
Sites Found:4
Alternate Views
Choose an alternate view: Map XML CSV Financials Report
Results View Options

Results by Site Impact

Change results view to: Name and Location Contaminants and Media

FCSI Identifier
Site Name
Status Fiscal Year Classification Highest Step Completed
00008691
Burwash CFTA
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00013150
LONGSPUR LAKE (LANG LAKE) (Waterlot)
Detailed testing completed. No further action required. 2015-2016 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
00026732
228 - Brunswick House - 06162 - MOUNTBATTEN 76A - ON04915922
Initial testing completed. Detailed testing underway. 2023-2024 I Insufficient Information 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00027887
Sturgeon River at Upper Goose Falls
Detailed testing completed. Remedial action plan under development. 2023-2024 N Not a Priority for Action 06 Classify the site using the CCME National Classification System