Results by Site Impact
Change results view to: Name and Location Contaminants and Media
FCSI Identifier Site Name |
Status | Fiscal Year | Classification | Highest Step Completed |
---|---|---|---|---|
00000466
142 - Albany - 06258 - FORT ALBANY 67 - 3000106598 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00000512
142 - Albany - 06258 - FORT ALBANY 67 - 3000051496 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00002431
Nagagami AWS, ON |
Initial testing completed. No further action required. | 2009-2010 | 03 Initial Testing Program | |
00003070
North French River near the mouth |
Confirmatory sampling completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00005274
144 - Moose Cree First Nation - 06261 - FACTORY ISLAND 1 - 0402548205 |
Historical review completed. Initial testing underway. | 2023-2024 | 02 Historical Review | |
00006526
182 - Constance Lake - 06294 - CONSTANCE LAKE 92 / 3000072096 |
Detailed testing completed. No further action required. | 2012-2013 | 2 Medium Priority for Action | 05 Detailed Testing Program |
00011375
Little Current River at Percy Lake |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00011421
Kenogami River near Mammamattawa |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00012510
RAPIDE-DANSEUR (HEBECOURT LAKE, SCH) |
Historical review not required. | 2015-2016 | 01 Identify Suspect Sites | |
00012704
HEARST (STE.THERESE LAKE) (Unassessed) |
Historical review not required. | 2012-2013 | 01 Identify Suspect Sites | |
00026654
142 - Albany - 06258 - FORT ALBANY 67 - ON04899219 |
Historical review completed. No further action required. | 2023-2024 | 02 Historical Review | |
00027735
Garage and Small Shed |
Detailed testing completed. Remediation / risk management planned. | 2023-2024 | 3 Low Priority for Action | 05 Detailed Testing Program |
00027736
Old town hall destroyed by fire |
Historical review completed. Initial testing underway. | 2023-2024 | 02 Historical Review | |
00027737
Warehouse destroyed by fire |
Detailed testing completed. Remediation / risk management planned. | 2023-2024 | 2 Medium Priority for Action | 05 Detailed Testing Program |
00027738
Storage Building |
Detailed testing completed. Remediation / risk management planned. | 2023-2024 | 2 Medium Priority for Action | 05 Detailed Testing Program |
00027739
Residence 217 |
Historical review completed. Initial testing underway. | 2023-2024 | 02 Historical Review | |
00027834
Albany River near Hat Island (Old Site) |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 3 Low Priority for Action | 06 Classify the site using the CCME National Classification System |
00027899
Albany River above Nottik Island |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00027900
Albany River near Hat Island (new site) |
Confirmatory sampling completed. No further action required. | 2022-2023 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00027940
Moose River above Moose River |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | N Not a Priority for Action | 06 Classify the site using the CCME National Classification System |
00027941
Missinaibi River below Waboose River |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 3 Low Priority for Action | 06 Classify the site using the CCME National Classification System |
05155009
144 - Moose Cree First Nation - 06261 - FACTORY ISLAND 1 - 3000042196 |
Initial testing completed. No further action required. | 2014-2015 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
05156005
142 - Albany - 06258 - FORT ALBANY 67 - 3000106398 |
Initial testing completed. Detailed testing underway. | 2023-2024 | I Insufficient Information | 03 Initial Testing Program |
05156006
142 - Albany - 06258 - FORT ALBANY 67 - 3000076396 |
Initial testing completed. Detailed testing underway. | 2023-2024 | I Insufficient Information | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
05156013
142 - Albany - 06258 - FORT ALBANY 67 - 3000076996 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
05156014
142 - Albany - 06258 - FORT ALBANY 67 / 3000077696 |
Initial testing completed. No further action required. | 2012-2013 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
11789001
Moose Factory (Weeneebayko) |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
32025001
GOCB - Moose Factory Island |
Remediation / risk management completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |