Search Results

Search Results Summary
Criteria:
  • Economic Region: Montréal
Select Additional Criteria...
Sort Key:FCSI Identifier (ascending)
Sites Found:206
Alternate Views
Choose an alternate view: Map XML CSV Financials Report
Results View Options

Results by Site Impact

Change results view to: Name and Location Contaminants and Media

FCSI Identifier
Site Name
Status Fiscal Year Classification Highest Step Completed
00000903
Parcel 1
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
00000904
Parcel 2
Detailed testing completed. No further action required. 2011-2012 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
00000909
Former Biotechnology Research Institute - Montreal
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00000919
Hangar 10 local 151 drilling in floor of an old shop
Initial testing completed. No further action required. 2009-2010   03 Initial Testing Program
00001284
Prairies River at Cheval Blanc Rapids
Historical review not required. 2014-2015   01 Identify Suspect Sites
00002327
Parcel 3
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
00002328
Parcel 4
Detailed testing completed. No further action required. 2011-2012 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
00008369
Garage Construction LAV III
Confirmatory sampling completed. No further action required. 2012-2013 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00008376
Multipurpose runway Montreal Garrison north side
Confirmatory sampling completed. No further action required. 2012-2013 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00008377
Construction of CSC building Montréal
Initial testing completed. No further action required. 2009-2010   03 Initial Testing Program
00008378
Installation of an APU at building L-193
Detailed testing completed. No further action required. 2013-2014 I Insufficient Information 07 Develop Remediation/Risk Management Strategy
00008379
Layout of a salt shelter
Remediation / risk management completed. No further action required. 2012-2013 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
00008398
Underground infrastructure replacement - Montréal Garrison
Initial testing completed. No further action required. 2016-2017   03 Initial Testing Program
00008400
100 tons balance
Confirmatory sampling completed. No further action required. 2013-2014 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
00008428
Access ramp and docks repairs Montréal Garrison
Initial testing completed. No further action required. 2009-2010   03 Initial Testing Program
00008466
200 places prkng Mtl Garrison
Remediation / risk management completed. No further action required. 2013-2014 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
00008505
Test banch building 15
Remediation / risk management completed. No further action required. 2013-2014 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
00008583
Putting drain arnd bldg L-42
Historical review not required. 2010-2011   01 Identify Suspect Sites
00008588
Behind Kitchen (B155) - Montreal garrison
Historical review not required. 2016-2017   01 Identify Suspect Sites
00008694
Montreal soccer pitch
Remediation / risk management completed. No further action required. 2017-2018 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
00012199
Upstream Rapides du Cheval Blanc, anterior
Historical review completed. No further action required. 2009-2010   02 Historical Review
00012200
Upstream Rapides du Cheval Blanc, posterior
Historical review completed. No further action required. 2009-2010   02 Historical Review
00012335
Varennes, tide gage
Historical review completed. No further action required. 2009-2010   02 Historical Review
00012436
Dixie - front range light
Detailed testing completed. No further action required. 2023-2024   05 Detailed Testing Program
00012442
Dixie
Historical review completed. No further action required. 2006-2007 I Insufficient Information 02 Historical Review
00012469
BAIE D'URFE
Confirmatory sampling completed. No further action required. 2012-2013 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00012987
Ste. Anne's Hospital
Initial testing completed. No further action required. 2015-2016   03 Initial Testing Program
00012988
Senneville Lodge
Initial testing completed. No further action required. 2007-2008   03 Initial Testing Program
00021755
Lachine (tide gauge, divested).
Historical review not required. 2013-2014   01 Identify Suspect Sites
00021766
Kaknawake
Historical review completed. No further action required. 2012-2013   02 Historical Review
00021770
Sainte-Anne-de-Bellevue (rear range light)
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00021771
Sainte-Anne-de-Bellevue
Initial testing completed. No further action required. 2008-2009 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00021775
Beaconsfield (SAR/RER station)
Historical review completed. No further action required. 2015-2016   02 Historical Review
00021776
Pointe Quenet, ancien point géodésique, cédé
Initial testing completed. No further action required. 2012-2013   03 Initial Testing Program
00021777
Dorval, road to
Historical review completed. No further action required. 2012-2013   02 Historical Review
00021778
Dorval, road to
Historical review completed. No further action required. 2012-2013   02 Historical Review
00021779
Pointe Claire, quai de, ancien, FA, cédé
Historical review completed. No further action required. 2012-2013   02 Historical Review
00021780
Pointe Claire, Quai de - former rear light, divested.
Initial testing completed. No further action required. 2013-2014   03 Initial Testing Program
00021781
Lachine (rear range light)
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00021782
Lachine
Historical review completed. No further action required. 2012-2013   02 Historical Review
00021784
Sutherland, quai, ancien radar, cédé
Historical review completed. No further action required. 2012-2013   02 Historical Review
00021785
Jacques Cartier Bridge pier
Historical review completed. No further action required. 2009-2010   02 Historical Review
00021789
Tétreaultville
Initial testing completed. No further action required. 2008-2009 N Not a Priority for Action 03 Initial Testing Program
00023293
Site 9.1.1
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00023376
Site 1.2.1
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00024579
Highway 15
Initial testing completed. No further action required. 2011-2012   03 Initial Testing Program
00024597
Technoparc (industrial park) - Saint-Laurent
Confirmatory sampling completed. No further action required. 2012-2013 I Insufficient Information 09 Confirmatory Sampling and Final Reporting
00025774
Montreal Harbour
Initial testing completed. No further action required. 2019-2020   03 Initial Testing Program
00025804
Institute for Aerospace Research, Montreal
Initial testing completed. No further action required. 2020-2021   03 Initial Testing Program
00026389
Highway 15, between Atwater and Gaetan-Laberge, Verdun, Montreal
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00026458
Atwater Boulevard, North of HWY 15, Montreal
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00026459
Boulevard Atwater, South of HWY 15, Montreal
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00026460
Boulevard LaSalle, South of HWY 15, Montreal
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00026461
Wellington Street, North of HWY 15, Montreal
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00026462
Gaetan-Laberge Boulevard, South of HWY 15, Montreal
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00026463
Gaetan-Laberge Boulevard, North of HWY 15
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00026464
Nun's Island Boulevard, Montreal
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00026465
Rene-Levesque Boulevard, North of HWY 15, Nun's Island
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00026466
Rene-Levesque Boulevard, South of HWY 15, Nun's Island
Initial testing completed. No further action required. 2023-2024   03 Initial Testing Program
00026468
Nun's Island, Montreal
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00026469
Brossard
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00027712
Ile Sainte-Hélène
Detailed testing completed. Remediation / risk management planned. 2023-2024 I Insufficient Information 05 Detailed Testing Program
00027713
JCP- section 8 (entre Viger et Maisonneuve Est)
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 I Insufficient Information 08 Implement Remediation/Risk Management Strategy
00027714
JCP- section 7 (Terrains au sud de Viger)
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00027715
JCP- section 9 (entre Ontario et Maisonneuve Est)
Detailed testing completed. Remediation / risk management planned. 2023-2024 I Insufficient Information 05 Detailed Testing Program
00027716
AB- Section 10
Detailed testing completed. Remediation / risk management planned. 2023-2024 I Insufficient Information 05 Detailed Testing Program
00027758
Champlain Bridge
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
00027760
ETAP_approche_nord
Detailed testing completed. Remediation / risk management planned. 2023-2024   05 Detailed Testing Program
00027762
Pont Clément
Detailed testing completed. Remediation / risk management planned. 2023-2024   05 Detailed Testing Program
00027763
Pont Contournement
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00028004
MMC
Initial testing completed. Detailed testing underway. 2022-2023 1 High Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06953001
New Storage Area in Back of the Building
Confirmatory sampling completed. No further action required. 2013-2014 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
06959001
Canal sediments
Detailed testing completed. No further action required. 2014-2015 1 High Priority for Action 05 Detailed Testing Program
06959003
Site 10.2
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959004
Site 11.2
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959005
Site 11.3
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959006
Site 12.2
Confirmatory sampling completed. No further action required. 2013-2014 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
06959007
Site 13.3
Confirmatory sampling completed. No further action required. 2020-2021 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
06959008
Site 13.4
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959009
Site 13.6
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
06959010
Site 13.8
Detailed testing completed. Remedial action plan under development. 2023-2024 1 High Priority for Action 06 Classify the site using the CCME National Classification System
06959011
Site 13.9
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
06959012
Site 14.1.1
Detailed testing completed. No further action required. 2013-2014 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
06959013
Site 14.2
Detailed testing completed. No further action required. 2013-2014 3 Low Priority for Action 05 Detailed Testing Program
06959014
Site 14.7
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
06959015
Site 15.1
Detailed testing completed. Remediation / risk management planned. 2023-2024 2 Medium Priority for Action 05 Detailed Testing Program
06959017
Site 15.4
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
06959018
Site 15.5
Detailed testing completed. No further action required. 2021-2022 2 Medium Priority for Action 05 Detailed Testing Program
06959019
Site 03.1
Detailed testing completed. Remedial action plan under development. 2023-2024 1 High Priority for Action 06 Classify the site using the CCME National Classification System
06959020
Site 03.2.1
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959021
Site 03.2.2
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959022
Site 03.4
Confirmatory sampling completed. No further action required. 2013-2014 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
06959023
Site 04.1.1
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959024
Site 04.1.2
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959025
Site 04.1.3
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959026
Site 04.2.1
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959027
Site 04.2.2
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959028
Site 04.3
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
06959029
Site 04.4
Initial testing completed. No further action required. 2022-2023 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959030
Site 08.3
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959031
Site 09.3.1
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959032
Site 09.3.2
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959033
Site 11.1
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959034
Site 13.5
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
06959035
Site 01.1
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959036
Site 01.2
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
06959037
Site 01.3
Detailed testing completed. No further action required. 2013-2014 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
06959038
Site 02.1
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959040
Site 02.2.0
Detailed testing completed. No further action required. 2013-2014 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
06959042
Site 03.2.3
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959043
Site 03.2.4
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959044
Site 03.3
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959045
Site 03.5
Initial testing completed. No further action required. 2022-2023 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959046
Site 04.2.3
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959047
Site 04.5
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
06959048
Site 04.6
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959049
Site 04.7
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
06959050
Site 05.1
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959051
Site 05.2
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959052
Site 05.4
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
06959053
Site 06.1
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959054
Site 06.2
Initial testing completed. No further action required. 2013-2014 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959055
Site 07.1 (north deposit site)
Remediation / risk management completed. No further action required. 2013-2014 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
06959056
Site 07.2
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959057
Site 07.3
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
06959058
Site 08.1
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959059
Site 08.2
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959060
Site 8.4
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959061
Site 08.5
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959062
Site 08.6 (north deposit site)
Remediation / risk management completed. No further action required. 2013-2014 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
06959063
Site 09.1 (North deposit site)
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
06959064
Site 09.2
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959065
Site 09.3.3
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959066
Site 09.4
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959067
Site 10.1
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
06959068
Site 10.3
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959069
Site 10.4
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959070
Site 10.5
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959071
Site 10.6
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959072
Site 11.4
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959073
Site 11.5
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959074
Site 11.6
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959075
Site 11.7
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959076
Site 13.10
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
06959077
Site 13.1.1
Initial testing completed. Detailed testing underway. 2023-2024 I Insufficient Information 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959078
Site 13.1.2
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959079
Site 13.1.3
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06959080
Site 13.11
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
06959081
Site 13.2
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
06959082
Site 13.7
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
06959084
Site 14.3
Remediation / risk management completed. No further action required. 2021-2022 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
06959085
Site 14.4
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
06959086
Site 15.2
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
06959088
Site 15.6
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
06959089
Site 15.7
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
06959090
Site 16.1 Peel Basin
Detailed testing completed. No further action required. 2013-2014 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
06959091
Site 02.3
Initial testing completed. Detailed testing underway. 2023-2024 I Insufficient Information 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
06972001
Pointe-Picard Marina - Marine sediments
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
06985001
Former firefighter training site
Detailed testing completed. No further action required. 2011-2012 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
06985002
Depot C - occupied by lessee
Remediation / risk management completed. No further action required. 2011-2012 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
06985003
Vacant site (lot 12) -firefighter training site No. 2
Remediation / risk management completed. No further action required. 2011-2012 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
06985004
Lot 9 - former petroleum depot
Remediation / risk management completed. No further action required. 2011-2012 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
06985005
FEC- Field Electrical Center
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
06985006
Site H
Remediation / risk management completed. No further action required. 2011-2012 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
06985007
Vacant site (lot 12)
Confirmatory sampling completed. No further action required. 2008-2009 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
06985008
Air Navigation Facility: RAMP - Terminal Surveillance Radar
Confirmatory sampling completed. No further action required. 2008-2009 I Insufficient Information 09 Confirmatory Sampling and Final Reporting
07013001
Building E
Long term monitoring completed. No further action required. 2022-2023 N Not a Priority for Action 10 Long-Term Monitoring (Optional)
07013002
Outside Building B
Detailed testing completed. No further action required. 2022-2023 I Insufficient Information 05 Detailed Testing Program
07048001
Normand-Maurice Building
Confirmatory sampling completed. No further action required. 2009-2010 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
07070002
Former Building 12
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
07070004
Soil assessment building 166
Confirmatory sampling completed. No further action required. 2013-2014 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
07070005
Enlargement of LAV III testing ramp at 202 WKP
Confirmatory sampling completed. No further action required. 2013-2014 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
07089001
Cathcart Armoury
Remediation / risk management completed. No further action required. 2013-2014 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
07156001
St-Grégoire Armoury
Confirmatory sampling completed. No further action required. 2013-2014 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
07221001
Longue Pointe Soil Clean-up
Long term monitoring completed. No further action required. 2013-2014 N Not a Priority for Action 10 Long-Term Monitoring (Optional)
07221002
Mechanical Workshop, L-3, ASU Longue-Pointe South
Long term monitoring completed. No further action required. 2013-2014 N Not a Priority for Action 10 Long-Term Monitoring (Optional)
07221003
Loading platform, L-3 North, ASU LP 
Historical review completed. No further action required. 2016-2017   02 Historical Review
07221004
Parking at south L-6, ASU LP 
Remediation / risk management completed. No further action required. 2013-2014 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
07221005
L-10 South, ASU LP 
Remediation / risk management completed. No further action required. 2013-2014 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
07221006
Outdoor Firing Range L-139, ASU LP 
Initial testing completed. No further action required. 2009-2010   03 Initial Testing Program
07221007
Parking - South Section (Notre Dame) ASU LP 
Long term monitoring completed. No further action required. 2013-2014 N Not a Priority for Action 10 Long-Term Monitoring (Optional)
07221008
Used snow sites, ASU LP 
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
07221018
Sector Slag Studies, ASU LP
Remediation / risk management completed. No further action required. 2011-2012 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
07221019
Mechanical Workshop L-3 North, ASU LP 
Confirmatory sampling completed. No further action required. 2013-2014 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
07221020
Central thermal retaining wall, Bldg 37 Montreal Garrison 
Confirmatory sampling completed. No further action required. 2014-2015 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
07221021
Indoor Firing Range L-123, ASU LP 
Initial testing completed. No further action required. 2009-2010   03 Initial Testing Program
27055001
46 St-Jacques, Montreal
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
30939001
643,645, 655 and 655A Montée de Liesse; Lots 1 892 534 and 1 892 535
Confirmatory sampling completed. No further action required. 2016-2017 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
55380001
Old Port of Montreal - Confinement Cell
Remediation / risk management completed. No further action required. 2021-2022 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
55380002
Old Port of Montreal
Remediation / risk management completed. No further action required. 2008-2009 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
55380003
Old Port of Montreal
Remediation / risk management completed. No further action required. 2008-2009 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
55380004
Old Port of Montreal
Remediation / risk management completed. No further action required. 2008-2009 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
55380006
Old Port of Montreal
Remediation / risk management completed. No further action required. 2008-2009 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
55380007
Old Port of Montreal
Remediation / risk management completed. No further action required. 2008-2009 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
55380008
Old Port of Montreal
Remediation / risk management completed. No further action required. 2008-2009 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
55380009
Old Port of Montreal
Remediation / risk management completed. No further action required. 2008-2009 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
55380010
Old Port of Montreal
Remediation / risk management completed. No further action required. 2008-2009 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
55380011
Old Port of Montreal
Remediation / risk management completed. No further action required. 2008-2009 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
55380012
Old Port of Montreal
Remediation / risk management completed. No further action required. 2008-2009 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
55380013
Old Port of Montreal
Remediation / risk management completed. No further action required. 2008-2009 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
55380014
Old Port of Montreal
Remediation / risk management completed. No further action required. 2008-2009 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
55380015
Old Port of Montreal
Remediation / risk management completed. No further action required. 2008-2009 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
55380016
Old Port of Montreal
Remediation / risk management completed. No further action required. 2008-2009 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
55380017
Old Port of Montreal
Remediation / risk management completed. No further action required. 2008-2009 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
55380019
Old Port of Montreal - Horloge Basin
Remediation / risk management completed. No further action required. 2008-2009 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
82115001
Tétreaultville - front range light
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)